Moore Road    

 



The current closure of Moore immediately west of Thornydale, the road will be reopened to through traffic by March 5th. The originally scheduled timeframe for reopening the road was the end of January. But utility conflicts and weather have caused a delay until the beginning of March.

The opening of the new segment of Moore Road from Camino de Oeste to Dove Mountain is scheduled to be open by the end of April.

Town of Marana Construction Letter 

 

  

View from DM Blvd  East Toward Oro Valley April 2015

  

View East from Camino De Oeste to Oro Valley March 2015

Map of Moore Road Link

 

 

 
.
   